To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behavior or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.Privacy Policy

Free template · Deal execution

Software Pilot Plan Template

A software pilot plan template is a written plan for letting a limited group of real users run B2B software in their daily work before a full purchase. It covers scope, the pilot group, success metrics agreed with the buyer, a weekly timeline, owners on both sides, check-ins, exit criteria and the decision meeting.

Last updated: By Kavyashree SBFree template, files emailed to your work address

Get the files by email

Free. We email the Word, Excel and PDF versions to your work address.

Formats to send:

What a software pilot plan template is

A pilot puts the software into production with a small group of real users for a fixed period, usually once the buyer is satisfied that the product works technically. It answers a different question from a proof of concept. A POC proves technical fit: whether the product connects to the buyer's systems, handles their data and meets their security requirements. A pilot proves adoption and value: whether the buyer's people will use it in their real work, and whether that work improves in a way someone can measure.

Because a pilot runs on real work, its success metrics are about behaviour and results. Typical examples are how many of the pilot group use the product each week, how long a routine task takes before and after, and whether an output a manager already reviews gets better. Each metric needs a baseline measured before the pilot starts, and the buyer has to agree the metrics in writing. Otherwise the end of the pilot becomes a debate about what good looks like.

The commercial side needs as much planning as the pilot itself. A pilot can be free, paid, or paid with the fee credited against the first-year contract. Whichever it is, both sides should write down before the start what turns the pilot into a contract, meaning the exit criteria and the terms that apply if they are met, and book the decision meeting at kickoff. Some sellers agree the order form in advance, with a start date that depends on the pilot result.

Small, short pilots give the clearest answers. One team or one region, a fixed number of weeks and a decision date in everyone's calendar is usually enough. A pilot that grows while it runs, or is extended without a decision, tends to turn into an unpaid rollout that neither side planned.

When to run a software pilot

  • The technical questions are settled, and the buyer now wants to know whether their people will actually use it.
  • The economic buyer will approve the budget only with evidence from their own team's work.
  • The full rollout is large enough that a mistake would be expensive, so the buyer wants to start with one team or region.
  • The main risk is change management: the software replaces a habit, a spreadsheet or another tool.
  • Do not offer a pilot while the buyer still doubts technical fit. Run a proof of concept first.

Pilot vs proof of concept vs free trial vs phased rollout

A pilot and a POC are often confused, and some deals need both, in that order. Agree with the buyer which one you are running, because each needs different people, a different environment and different success measures.

Pilot vs proof of concept vs free trial vs phased rollout
TypeWhat it provesWho takes partEnvironmentEnds with
PilotAdoption and value with real usersA limited group of real users doing their normal workProduction, with real dataA contract and rollout decision against agreed metrics
Proof of conceptTechnical fitA small technical and evaluation teamSandbox or test tenantA scored decision against technical criteria
Free trialIndividual interestIndividual users, usually self-serveVendor-hosted, often with sample dataA purchase or nothing, often with no agreed criteria
Phased rolloutNothing new; it delivers what was boughtSuccessive teams after the contract is signedProductionFull deployment

The software pilot plan template

Fill in the charter and the success metrics first, measure the baselines and get the buyer's executive sponsor to sign off before anyone is given an account. Then name the pilot group and the owners, date the timeline back from the decision meeting and agree the exit criteria. Results and the decision are recorded at the end.

Pilot charter

Pilot charter
FieldWhat to write
Business goal[The outcome the full purchase is meant to deliver, in the buyer's words]
What the pilot must prove[The adoption and value questions; technical fit should already be settled]
In scope[The workflows the pilot group will use it for]
Out of scope[Teams, features and integrations that are not part of the pilot]
Pilot group[Team, region or role; number of users; why this group represents the wider rollout]
Start date / end date / decision meeting[Date] / [date] / [date, booked at kickoff]
Commercial terms of the pilot[Free / paid / paid and credited against the contract; any services included]
What converts the pilot into a contract[If the exit criteria are met, the buyer signs (order form or contract) for (scope) starting (date)]
Signed off by[Buyer executive sponsor and seller lead, with date]

Pilot group

Pilot group
NameRoleTeam or regionWhy includedManager
[Name][Role][Team][Typical user / heavy user / sceptic][Name]
[Name][Role][Team][Reason][Name]
[Name][Role][Team][Reason][Name]

Success metrics (agreed with the buyer)

Success metrics (agreed with the buyer)
Success metricBaseline before the pilotTarget by the endHow and where it is measuredBuyer ownerResult
Adoption: [how many of the pilot group use it each week][Usually none, for a new tool][Number of users each week from week (n)][Usage report, checked by the buyer][Name][Met / partly met / not met]
Time: [a routine task done faster][Measured over the two weeks before the start][Target time][Time log or system timestamps][Name][Result]
Quality: [an output a manager already reviews][Current level][Target level][The review the manager already does][Name][Result]
User view: [would the pilot group keep it][Not applicable][Agreed threshold][Short survey in the final week][Name][Result]

Owners on both sides

Owners on both sides
RoleBuyer ownerSeller ownerResponsible for
Executive sponsor[Name][Name]Signing off the metrics and attending the decision meeting
Pilot lead[Name][Account executive]Running the plan week to week and calling the mid-point review
Pilot group manager[Name]Not applicableMaking time for the pilot group and keeping them on the new way of working
Admin and IT[Name][Solutions engineer or implementation lead]Accounts, single sign-on, integrations and data access
Training and support[Name][Customer success or onboarding lead]Training the pilot group and answering questions during the pilot
Commercial[Procurement or budget owner][Account executive]Pilot terms, the order form and the conversion terms

Timeline by week

Timeline by week
WeekMilestoneOwnerDone when
Before week 1Baselines measured; charter and metrics signed offBoth pilot leadsBuyer sponsor has approved them in writing
Before week 1Accounts, single sign-on and integrations readyAdmin and IT ownersEvery pilot user can sign in and see their own data
Week 1Kickoff and trainingTraining and support ownersEvery pilot user trained on the in-scope workflows
Week 2First real work in the productPilot groupEvery user has completed the core workflow at least once
Week 3Mid-point reviewBoth pilot leadsUsage and metrics reviewed, blockers named, scope confirmed
Weeks 4-5Steady usePilot group and their managerUsage holds without reminders from the seller
Week 6Final measurement and surveyBuyer pilot leadEvery metric measured against its baseline
Week 7Decision meetingExecutive sponsorsConvert, extend with a defined change, or stop

Check-ins

Check-ins
Check-inWhenAttendeesQuestions to answer
Weekly pilot check-in[Same time each week, 30 minutes]Both pilot leads and the pilot group managerWho is using it, what is blocking the rest, what to fix this week
Mid-point review[End of week 3]Pilot leads, with both executive sponsors invitedAre the metrics on track, and does scope need to change
Sponsor update[Every two weeks, by email]Executive sponsorsProgress against metrics, decisions needed from the sponsor

Exit criteria and decision meeting

Exit criteria and decision meeting
FieldWhat to write
Exit criteria to convert[Which metrics must be met, and whether all of them or a named subset]
Exit criteria to stop[What result would end the evaluation]
Decision meeting date and attendees[Booked at kickoff; both executive sponsors and both pilot leads]
Decision options[Convert to contract / extend once, with a defined change and a new end date / stop]
If converting[Order form, contract start date and the rollout plan for the next teams]
Accounts and data at the end[What happens to accounts and pilot data if the pilot stops, and if it converts]

Prefer a file? We email the Word, Excel and PDF versions to your work address, free.

Email me the files

Software pilot plan example

Example: fictional company

Here is the template filled in for an invented six-week paid pilot that followed a successful proof of concept. The metrics and baselines were agreed in one meeting with the buyer's revenue operations team and signed off before any pilot user had an account.

Ferncastle Analytics (seller) has passed a technical POC with Marlow & Finch Logistics (buyer). The POC showed the CRM data arrives correctly; the pilot has to show that a whole region will run its weekly forecast in Ferncastle and stop rebuilding it in spreadsheets.

Pilot charter

Pilot charter
FieldExample entry
What the pilot must proveThat the northern region's managers and account managers use Ferncastle for the weekly forecast and stop using the spreadsheet
Pilot groupNorthern region: Luis Moreno, Regional Sales Manager, two team leads and nine account managers (12 users)
DatesWeeks 1-6; decision meeting booked for week 7
Commercial terms of the pilotPaid pilot; the fee is credited against the first-year contract if Marlow & Finch converts
What converts the pilot into a contractIf the first three metrics are met, Marlow & Finch signs the agreed order form for all five regions, starting the first Monday after signature
Signed off byDana Okafor, Director of Revenue Operations, and Sam Whitley, Account Executive

Success metrics and results

Success metrics and results
Success metricBaseline before the pilotTarget by the endHow and where it is measuredBuyer ownerResult
Pilot users active in Ferncastle each weekNone (new tool)At least 10 of 12 each week from week 3Ferncastle usage reportGrace Lindqvist, Sales Operations AnalystMet: 11 of 12 from week 3
Time Luis spends preparing the weekly forecast callAbout 3 hours, logged over the two weeks before the pilotUnder 1 hourLuis's own time logLuis MorenoMet: about 40 minutes by week 5
Weekly forecast submitted from Ferncastle with no spreadsheetSpreadsheet every weekEvery week from week 2Submission log kept by revenue operationsDana OkaforMet in weeks 2-6
Next steps recorded on every forecast deal before the callFewer than half of forecast dealsEvery forecast dealCRM field check before each callGrace LindqvistPartly met: two account managers still lagging in week 6

Decision meeting record

Decision meeting record
FieldExample entry
DecisionConvert to contract
ConditionsFerncastle runs a 30-minute refresher for the two account managers who were lagging, before rollout to the next region
Next stepOrder form signed in week 8; the account executive hands the account to customer success the same week

Example: fictional company. Ferncastle Analytics, Harborview Metrics, Marlow & Finch Logistics and every person named in this example are invented for illustration. Any resemblance to real companies or people is coincidental.

How to run a software pilot

  1. Settle technical fit first

    If the buyer still has questions about integration, data or security, answer them with a proof of concept or an architecture review before the pilot. A pilot slowed by technical problems measures the problems and tells you little about adoption.

  2. Measure baselines before the start

    Agree the metrics with the buyer, then measure each one for a week or two before anyone gets an account. Without a baseline, a good result at the end is only an impression.

  3. Choose a pilot group that looks like the rollout

    Pick a team whose work is typical of the teams that will follow, with a manager who will make time for it. A group made up only of enthusiasts gives a result the rest of the organisation will not believe.

  4. Agree what converts the pilot before kickoff

    Write down the exit criteria, the contract terms that apply if they are met and the date of the decision meeting. Then the end of the pilot is a decision both sides prepared for.

  5. Check in every week and review at the mid-point

    A short weekly check-in catches users who have stopped logging in while there is still time to help them. At the mid-point, review the metrics with both sponsors and cut scope if a part of the pilot is not going to finish.

  6. Hold the decision meeting on the date set at kickoff

    Present each metric against its baseline and record the decision: convert, extend once with a defined change, or stop. If converting, move straight to the order form and the handoff to customer success.

Common software pilot mistakes

Using a pilot to settle technical doubts

Real users hitting integration problems in week one will judge the product on those problems. Prove technical fit first, then pilot.

No baseline

If nobody measured how long the task took before, nobody can show it is faster now. Measure before the start.

A pilot group of enthusiasts

Volunteers who already wanted the tool will use it anyway. Include typical users, and at least one sceptic, so the result means something to the teams that follow.

Extending without a decision

An extension with no new end date and no defined change becomes free use of the product. Allow one extension at most, with its own date and reason.

Commercial terms left until the end

If the conversion terms are negotiated after a successful pilot, the buyer has the evidence and the seller has no date. Agree them before kickoff.

The seller doing the users' work

If the seller's team runs reports or enters data for the pilot group, the pilot measures the seller's effort. Support the users and leave the work to them.

How Revspire runs this template

In Revspire Digital Sales Rooms, the pilot plan can sit in the buyer's room as a mutual action plan with owners and due dates, next to the agreed metrics, training material and check-in notes. Buyer engagement analytics show whether the pilot group and the executive sponsor are looking at what you share.

Software pilot plan template FAQs

What is the difference between a pilot and a proof of concept?

A proof of concept proves technical fit: whether the product works with the buyer's systems, data and security requirements, tested by a small evaluation team. A pilot proves adoption and value: whether real users take it up in their daily work and whether agreed metrics improve. When a deal needs both, the POC comes first.

How long should a software pilot last?

Long enough for the pilot group to settle into using it and for the metrics to show a trend, and no longer. Plan it in weeks, with a fixed end date. Set the length from the metrics, book the decision meeting at kickoff and treat any extension as a decision both sponsors approve.

How many users should be in a pilot group?

Enough to be representative of the rollout and few enough to support well. One team or one region is common. Include typical users and their manager, plus at least one sceptic, so that the result is credible to the teams that will follow.

Should a B2B software pilot be paid?

Often, yes, especially when it runs in production and needs setup and training. A common structure is a paid pilot with the fee credited against the first-year contract if the buyer converts. A fee also means the buyer plans real time for the pilot group. Write the terms in the charter either way.

What are good success metrics for a software pilot?

Metrics the buyer already cares about and can measure: weekly active use by the pilot group, time taken for a routine task, the quality of an output a manager already reviews, and whether users would keep the tool. Each needs a baseline measured before the pilot starts and a target agreed in writing.

Related templates and reading

Browse all free sales templates

A walkthrough built around you

Accelerate Revenue Velocity.

See how Revspire brings content, coaching, buyer collaboration, and deal execution into one focused revenue workspace.

  • Know what assets drive revenue
  • See why deal-room deals win 35% vs 28%.
  • Cut onboarding time in half
SOC 2 Type II certified

Request Demo

See this template filled in against a real deal, with the buyer side of it live in a deal room.

I'm interested in: